UTPAL TREHAN versus DLF HOME DEVELOPERS LTD.

[2022] 15 S.C.R. 458 · 2022 INSC 688

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

A flat booked in March 2008 in a Gurgaon project was to be delivered within 36 months, which the builder's letter of 26.03.2009 made run from the date of booking with delay compensation doubled to Rs 10 per sq ft per month. The builder's offer of possession in June 2013 came with a statement of account found illegal because it denied rebates for a nine-day delay in an instalment on an unproved demand notice. The State Commission awarded delay compensation from March 2011 until a fresh offer of possession but directed the allottee to pay maintenance charges; the National Commission substituted 6% interest from July 2013 following Arifur Rahman Khan. The Supreme Court restored the State Commission's compensation: the builder's own enhanced term governed and the Arifur Rahman Khan ratio, concerning a one-sided agreement, did not apply;

Issues

  1. Whether consumer fora may direct a flat allottee to pay maintenance charges to the builder when the builder's own case is that the charges belong to an independent maintenance association that is not a party and has made no claim.
  2. Whether delay compensation should be awarded at the contractual rate as enhanced by the builder, or replaced by interest under Arifur Rahman Khan v. DLF Southern Homes.
  3. Whether an offer of possession conditioned on payment of a statement of account found to be illegal is a valid offer that stops the running of delay compensation.
  4. From which date delay compensation runs where the builder has amended the possession clause to run from the date of booking.

Provisions considered

Held

Result

Appeals disposed of: the directions requiring the allottee to pay maintenance charges set aside; fresh offer of possession to be issued and conveyance executed within eight weeks; delay compensation at Rs 10 per sq ft per month from March 2011 till the fresh offer, adjusting sums already paid and the early payment rebate; costs of Rs 50,000 retained; other findings of the National Commission undisturbed.