Supreme Court of India · 02/09/2025

OIL AND NATURAL GAS CORPORATION LTD. versus M/S G & T BECKFIELD DRILLING SERVICES PVT. LTD.

[2025] 9 S.C.R. 507 · 2025 INSC 1066

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

ONGC challenged an arbitral award, as affirmed by the Gauhati High Court under Section 37, only to the extent that it granted 12% interest on the awarded sum from the date the statement of claim was affirmed, contending that clause 18.1 of the contract barred interest on delayed or disputed payments. The Supreme Court held that an arbitral tribunal's power under Section 31(7)(a) to award pendente lite interest is excluded only where the contract bars it expressly or by necessary implication; a clause merely denying interest on delayed payment is not readily inferred as such a bar. Clause 18.1 did not bar pendente lite interest, and the appeal was dismissed.

Issues

  1. Whether clause 18.1 of the agreement, which stated that no interest would be payable by ONGC on any delayed payment or disputed claim, barred the arbitral tribunal from awarding pendente lite interest on the sum awarded.
  2. What is the scope of the arbitral tribunal's power to award interest for the pre-reference, pendente lite and post-award periods under Section 31(7) of the Arbitration and Conciliation Act, 1996, and when can that power be treated as excluded by agreement.

Provisions considered

Held

Result

Appeal dismissed; the arbitral award, including the award of pendente lite interest at 12% per annum from the date the statement of claim was affirmed, as affirmed by the High Court, left undisturbed; pending applications disposed of.