Supreme Court of India · 04/07/2017

ASSAM STATE ELECTRICITY BOARD AND ORS. versus BUILDWORTH PVT. LTD.

[2017] 7 S.C.R. 123 · 2017 INSC 587

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Court upheld the arbitrator’s awards for extended-period escalation and idling charges under the 1940 Act. The contract construction was supported by correspondence and conduct, and contributory delay had been considered. It restored interest entitlement from the written demand, modifying the rate and specifying the periods payable.

Issues

  1. Whether the escalation ceiling barred extended-period claims and contributory delay invalidated idling compensation.
  2. Whether interest could precede quantification of damages and from what date.

Provisions considered

Held

Result

Board’s appeal dismissed; claimant’s appeal allowed in the stated terms. Interest fixed at 12% annually from 20 April 1987 to 31 December 1997 and from the trial-court decree until payment or realization. No costs.

Judgment PDF: Supreme Court of India, [2017] 7 S.C.R. 123.