VidhiSangh

Supreme Court of India · 25/08/2025

CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LTD. (CESC) versus SAISUDHIR ENERGY (CHITRADURGA) PVT. LTD. & ANR.

[2025] 8 S.C.R. 1493 · 2025 INSC 1034

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

A solar power developer failed to achieve commercial operation under a power purchase agreement because the State transmission utility had not commissioned the evacuation lines; the distribution licensee encashed the performance bank guarantee. The State Commission, affirmed by APTEL, treated the delay as force majeure and directed restoration of the guarantee, extension of timelines and renegotiation of tariff. The Supreme Court set those orders aside: the developer had neither sought extension under the PPA's extension clause nor given the mandatory force majeure notice, so the encashment was a remedy the contract conferred, and regulatory fora cannot rewrite a competitively bid, approved contract in the name of equity.

Issues

  1. What was the effect of the transmission utility's delay in commissioning the 220 kV evacuation lines on the PPA timelines for fulfilment of conditions precedent and achievement of commercial operation?
  2. Whether the distribution licensee was entitled to invoke and encash the performance bank guarantee under Article 4.4 of the PPA.
  3. Whether a finding of force majeure could be sustained when the notice required by Article 14.5 of the PPA was never given.
  4. Whether the PPA was a contingent contract so that the developer's obligations depended on completion of the evacuation system.
  5. Whether the State Commission and APTEL had jurisdiction to direct restoration of the bank guarantee, extension of timelines and renegotiation of tariff.

Provisions considered

Held

Result

Appeal allowed; APTEL judgment dated 21.03.2018 in Appeal No. 176 of 2015 and the State Commission's order dated 28.01.2015 in O.P. No. 24 of 2014 set aside; pending applications disposed of; no order as to costs.

Judgment PDF: Supreme Court of India, [2025] 8 S.C.R. 1493.