Supreme Court of India · 11/01/2021

IREO GRACE REALTECH PVT. LTD. versus ABHISHEK KHANNA & OTHERS

[2021] 2 S.C.R. 1 · 2021 INSC 13

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

In appeals concerning delayed apartments in The Corridors project, the Court computed the contractual deadline from fire approval, rejected oppressive buyer-agreement terms, and confirmed that RERA did not oust consumer remedies. Relief depended on the buyers’ position: two with completed, certified apartments had to accept possession with delay compensation, while buyers without occupancy certificates obtained refunds with interest. Specific refund directions applied to an unfulfilled undertaking and an urgent hardship case.

Issues

  1. From what date the contractual delivery period ran.
  2. Whether one-sided agreement terms bound buyers under the 1986 consumer law.
  3. Whether RERA displaced consumer-forum jurisdiction.
  4. Which buyers should accept possession and which were entitled to refund, and on what terms.

Provisions considered

Held

Result

Appeals disposed of with differentiated possession, delay-compensation and refund directions; no order as to costs.