Summary

The Court held that no concluded contract arose from the letter of intent and brief commencement of work in this tender. Performance security, the integrity pact and other stipulated formalities remained unfulfilled, so the employer could not recover the extra cost of engaging another contractor under the proposed contract’s risk-and-cost provision. Forfeiture of bid security remained permissible. The balance of the ten-lakh-rupee deposit was ordered refunded within two months, and the employer’s appeal was dismissed.

Issues

  1. Whether the tender documents, letter of intent and commencement of work established a concluded contract permitting risk-and-cost recovery.

Held

Result

Appeal dismissed with parties bearing their own costs; only bid-security forfeiture upheld and the balance of the deposit to be refunded within two months. Interim order discharged.