M/S INTERSTATE CONSTRUCTION versus NATIONAL PROJECTS CONSTRUCTION CORPORATION LTD.

[2025] 5 S.C.R. 2106 · 2025 INSC 699

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Court set aside a Division Bench judgment under Section 37 of the Arbitration and Conciliation Act, 1996 which had struck down an arbitral tribunal's pendente lite interest directions on the grounds that Section 31(7) recognises only two interest periods and that interest on principal plus pre-reference interest amounted to impermissible compound interest. Section 31(7)(a) gives the tribunal discretion to award interest for the whole or any part of the period from cause of action to award, to sub-divide that period, exclude a period of laches and apply different rates, and the 'sum' awarded on which post-award interest runs includes interest up to the award (Hyder Consulting), so neither reasoning was sustainable.

Issues

  1. Whether, under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, an arbitral tribunal may award interest separately for the pre-reference period and the pendente lite period, at different rates and excluding a period of laches, or whether the statute recognises only a single period from cause of action to award.
  2. Whether an arbitral tribunal awarding pendente lite and post-award interest on the principal amount together with interest already awarded for the earlier period levies impermissible compound interest.

Provisions considered

Held

Result

Appeal allowed; the Division Bench's judgment dated 01.08.2023 in the Section 37 appeal, which had set aside the interest directions in paragraph 58(b) of the award dated 28.10.2020, set aside; no order as to costs.