Supreme Court of India · 08/04/2019

TUKARAM S/O SADASHIV CHAUDHARI versus THE EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & ANR.

[2019] 5 S.C.R. 765 · 2019 INSC 471

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Compensation for a delayed agricultural electricity connection was enhanced from Rs 2 lakh to Rs 5 lakh. The applicant’s failure to submit the required test report explained the initial delay, but the electricity distributor offered no cogent explanation for the decade following submission of that report. The prolonged deprivation prevented use of a bore well and caused hardship warranting higher consumer compensation.

Issues

  1. Which period of delay was attributable to the electricity distributor.
  2. Whether Rs 2 lakh constituted fair compensation.

Held

Result

Appeal allowed without costs. Compensation enhanced to Rs 5,00,000, payable within four weeks; in default, compensation to carry 9% annual interest. Pending applications disposed of.