Supreme Court of India · 02/01/2025

KRISHNA DEVI @ SABITRI DEVI (RANI) M/S S.R. ENGINEERING CONSTRUCTION versus UNION OF INDIA & ORS.

[2025] 1 S.C.R. 81 · 2025 INSC 24

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Under the Arbitration Act, 1940, the notice of filing of an award required by Section 14(2), from which the 30-day limitation for objections under Article 119(b) of the Limitation Act runs, needs no particular form; awareness that the award is filed and accessible suffices. The respondents knew of the award from the District Judge's order of 21.09.2022, so limitation expired on 20.10.2022 and the appellant's Section 17 application of 10.11.2022 was not premature.

Issues

  1. Whether limitation for objecting to an award under the Arbitration Act, 1940 runs only from a formal court notice of filing of the award, or from the date the party becomes aware that the award has been filed.
  2. Whether the appellant's application under Section 17 of the 1940 Act for judgment in terms of the award was premature.

Provisions considered

Held

Result

Appeal allowed; the High Court's order dated 27.03.2024 in C.R.P. No. 138 of 2022 set aside; District Judge, Sonitpur directed to dispose of Misc. (J) No. 61 of 2022 expeditiously, preferably within five months; no order as to costs.