Summary

A High Court acting under Section 15(2) of the Arbitration and Conciliation Act, 1996 may only appoint a substitute arbitrator under the rules that governed the original appointment. It cannot declare the arbitral tribunal's earlier proceedings and orders a nullity, here on the ground that the corporate debtor was under an IBC moratorium. That part of the High Court's order was set aside, and under Article 142 the transactions made pursuant to the tribunal's orders were declared valid.

Issues

  1. Whether the High Court, while appointing a substitute arbitrator under Section 15(2) of the Arbitration and Conciliation Act, 1996, could declare the arbitral proceedings held between 17.03.2022 and 25.08.2022 a nullity because they took place during the moratorium under Section 14 of the IBC.
  2. What is the scope of a court's jurisdiction under Section 15(2), read with Sections 15(3) and 15(4), and how does it relate to Section 11?

Provisions considered

Held

Result

Appeal partly allowed and disposed of; the High Court's declaration that the arbitral proceedings on seven dates between 17.03.2022 and 25.08.2022 were a nullity set aside; transactions made pursuant to them declared valid under Article 142; the impugned order otherwise stands, as modified.