Summary

Applying the Section 11 framework discussed in this 2018 decision, the Supreme Court set aside appointment of an arbitrator because the contract had been discharged by accord and satisfaction. ANS had signed the final bill and no-claim certificate and voluntarily accepted final payment. Its later allegation of coercion lacked particulars or prima facie support. A genuinely disputed discharge obtained through fraud or coercion could permit arbitration, but a bare allegation did not suffice on these facts.

Issues

  1. Whether a later allegation of financial duress displaced the no-claim certificate and final settlement so as to justify appointing an arbitrator.

Held

Result

Appeal allowed; High Court’s order dated 12 January 2015 appointing an arbitrator set aside because no arbitrable dispute survived the established accord and satisfaction.