Supreme Court of India · 06/09/2021

M/S. INDSIL HYDRO POWER AND MANGANESE LIMITED versus STATE OF KERALA AND OTHERS

[2021] 13 S.C.R. 136 · 2021 INSC 449

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Court upheld contractual charges for the advantage of controlled water releases enjoyed by INDSIL’s and CUMI’s captive hydropower projects. The governing policy was incorporated in both agreements, and the negotiated terms were neither unconscionable nor manifestly arbitrary. Excluding independent producers supplying the electricity board was justified to avoid passing the charges to public consumers. The payments were contractual consideration for a benefit, not compulsory taxation. Both companies’ appeals were dismissed without costs, leaving the High Court’s judgment intact.

Issues

  1. Whether the projects derived the controlled-release benefit covered by their agreements and incorporated policy.
  2. Whether the contractual terms were unconscionable, manifestly arbitrary or discriminatory compared with independent power producers.
  3. Whether the water charges were unauthorized compulsory taxes rather than contractual payments.

Provisions considered

Held

Result

Appeals dismissed without costs; Division Bench judgment upholding contractual liability and its computation directions left intact.

Judgment PDF: Supreme Court of India, [2021] 13 S.C.R. 136.