Summary

In a continuing matter on recurrent flooding from the Ghaggar river affecting 25 villages in Punjab and Haryana, the Court had earlier directed the Central Water Commission to find a solution, and a mathematical model study was commissioned from CWPRS, Pune. The Central Water Commission reported that the final model study report had been forwarded to both States in September 2021. The Ghaggar Standing Committee had then concluded that the recommended short-term measures were the optimal solution for the States to adopt. These involve widening the river at feasible reaches and building embankments to limit the rise in water level. The Court directed Punjab and Haryana to implement the recommendations in a time-bound manner. It also required four-weekly stakeholder meetings and quarterly reports through the Committee and the Central Water Commission to the Court.

Issues

  1. What directions should issue to resolve the long-standing flooding of the Ghaggar basin affecting 25 villages, after the final mathematical model study report and its consideration by the Ghaggar Standing Committee.

Held

Result

Directions issued to the States of Punjab and Haryana to implement the recommendations, with periodic meetings and quarterly reports; the matter was listed for further hearing on 09.11.2022.