Summary

The Supreme Court directed the Collector to determine whether the claimant’s land had submerged before acquisition and to assess damages for the pre-notification period. The alleged loss of possession from 1991 was disputed and had not been categorically established. If prior submergence was found, Section 34 interest would also run from the Section 4 notification to the award. Pre-acquisition use or deprivation was to be addressed through damages, rather than statutory interest for that earlier period.

Issues

  1. Whether the claimant was entitled to pre-acquisition damages and statutory interest before the award in light of disputed earlier submergence.

Provisions considered

Held

Result

Appeal disposed of with directions to the Collector to determine the submergence and damages questions within six months after hearing the parties and evidence; additional Section 34 interest from notification to award conditional on the stated finding of prior submergence.