VidhiSangh

Supreme Court of India · 13/03/2023

GOVERNMENT OF NCT OF DELHI & ANR versus DAYANAND & ANR.

[2023] 2 S.C.R. 208 · 2023 INSC 219

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Land Acquisition Collector stated before the Delhi High Court that possession of nineteen of twenty biswas was taken by possession proceedings in April 2009 and that the landowner, served with a notice under Section 12(2) of the Land Acquisition Act, 1894 to collect compensation, never came, so the amount went to revenue deposit; the High Court nevertheless declared the acquisition lapsed under Section 24(2) of the 2013 Act, relying on Pune Municipal Corporation, for want of a categorical statement that compensation was paid. The Supreme Court allowed the appeal: Pune Municipal Corporation is overruled by Indore Development Authority, possession of the major portion was validly taken, and a landowner who ignores a notice to collect compensation cannot take advantage of his own conduct to plead non-payment.

Issues

  1. Whether an acquisition can be deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 where possession of the major portion of the land was taken by possession proceedings and the landowner, served with a notice to collect compensation, failed to collect it.

Provisions considered

Held

Result

Appeal allowed without costs; Delhi High Court judgment dated 12.09.2017 in W.P.(C) No. 1754 of 2015 quashed and set aside; writ petition dismissed and the acquisition held not to have lapsed under Section 24(2) of the 2013 Act.

Judgment PDF: Supreme Court of India, [2023] 2 S.C.R. 208.