Supreme Court of India · 31/01/2025

M/S C & C CONSTRUCTIONS LTD. versus IRCON INTERNATIONAL LTD.

[2025] 1 S.C.R. 1413 · 2025 INSC 138

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court upheld an arbitral award rejecting a contractor's delay-damages claims under clause 49.5 of the General Conditions of Contract, which bars damages for the employer's delay and provides only for extension of time. The contractor had repeatedly sought extensions under that clause and undertook not to claim anything beyond escalation, so it was estopped from challenging the clause; its new challenge under Sections 23 and 28 of the Contract Act could not be raised for the first time, and no ground for interference under Sections 34 and 37 was made out.

Issues

  1. Whether the contractor's claims for damages on account of the employer's delay were barred by clause 49.5 of the GCC.
  2. Whether the contractor, having sought extensions under clause 49 and given undertakings not to claim anything beyond escalation, could challenge the validity of clause 49.5.
  3. Whether the validity of clause 49.5 under Sections 23 and 28 of the Contract Act could be raised for the first time before the Supreme Court.
  4. Whether the employer had waived clause 49.5.
  5. The scope of interference with an award in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996.

Provisions considered

Held

Result

Appeal dismissed; the award rejecting the claims and the High Court's judgments under Sections 34 and 37 upheld.