VidhiSangh

Supreme Court of India · 15/05/2025

POWER GRID CORPORATION OF INDIA LIMITED versus MADHYA PRADESH POWER TRANSMISSION COMPANY

[2025] 5 S.C.R. 2062 · 2025 INSC 697

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The High Court erred in admitting writ petitions by a State transmission utility against CERC tariff orders that, while not condoning the delay in commissioning inter-State transmission assets, gave the Central transmission utility liberty to claim compensation from the State utility whose downstream delay caused it. The CERC exercises both regulatory and adjudicatory functions under Section 79(1) of the Electricity Act, 2003; absence of a regulation under Section 178 does not disable it from filling a regulatory gap by orders between the parties, such orders are appealable to APTEL under Section 111, no Whirlpool exception applied, and the writ petitions were dismissed leaving the merits to APTEL.

Issues

  1. Whether the CERC, in exercising its functions under Section 79(1) of the Electricity Act, 2003, is circumscribed by regulations made under Section 178, and whether the absence of a regulation on a subject bars it from passing orders on that subject.
  2. Whether the CERC exercises regulatory or adjudicatory functions under Section 79, and the scope of its power to regulate inter-State transmission and determine its tariff under clauses (c) and (d) of Section 79(1).
  3. Whether the grant of liberty to claim compensation for delay was a regulatory or adjudicatory function, and whether principles of natural justice required a specific prayer and a hearing of the party made liable.
  4. Whether the High Court was justified in admitting a writ petition under Article 226 against the CERC orders despite the statutory appeal to APTEL under Section 111.

Provisions considered

Held

Result

Appeals allowed; High Court judgment dated 25.02.2021 admitting the writ petitions set aside and both writ petitions dismissed; merits of the State utility's liability left open for APTEL under Section 111 if it appeals; pending applications disposed of; Registry directed to circulate the judgment to all High Courts.

Judgment PDF: Supreme Court of India, [2025] 5 S.C.R. 2062.