Summary

Adani Power Maharashtra had bid to supply 1320 MW to MSEDCL on the basis that 800 MW would be fuelled by the Lohara coal blocks allotted to it by the Ministry of Coal; after the bid cut-off date the Government of Maharashtra notified the area as part of the Tadoba Andheri Tiger Reserve buffer zone and the blocks were deallocated. MERC and APTEL concurrently held the deallocation a Change in Law, and APTEL directed that compensation be computed with the Lohara coal cost, including transportation, as the base. The Supreme Court dismissed MSEDCL's appeals: the buffer zone notification of 5 May 2010 was an order of a Governmental Instrumentality within the PPA's definition of 'Law', the deallocation was not the generator's fault, MSEDCL as a member of the Expert Committee could not resile from its recommendations, and the remaining issues were covered by earlier judgments.

Issues

  1. Whether deallocation of the bid-identified Lohara coal blocks, following the Government of Maharashtra's notification of a tiger reserve buffer zone after the bid cut-off date, amounts to a Change in Law under the PPA.
  2. Whether Change in Law compensation should be computed with the Lohara coal cost including transportation as the base, following the Expert Committee's transfer pricing methodology, rather than linkage coal cost.
  3. Whether the issues of domestic coal shortfall relief, SHAKTI Policy, carrying cost, station heat rate and gross calorific value warranted interference with APTEL's findings.

Provisions considered

Held

Result

Appeals dismissed; APTEL's judgment dated 5 October 2020 holding deallocation of the Lohara coal blocks to be a Change in Law and fixing the Lohara coal cost including transportation as the base for compensation upheld; pending applications disposed of; no costs.

Judgment PDF: Supreme Court of India, [2023] 7 S.C.R. 648.