VidhiSangh

Supreme Court of India · 11/05/2020

G H SOUTH EAST ASIA MARINE ENGINEERING AND CONSTRUCTIONS LTD. (SEAMEC LTD.) versus OIL INDIA LIMITED

[2020] 4 S.C.R. 254 · 2020 INSC 392

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Setting aside the award reimbursing diesel-price increases was upheld. Although courts must defer to a plausible arbitral interpretation, the tribunal’s expansion of the change-in-law clause contradicted the fixed-price contract read as a whole and the contractor’s obligation to supply fuel at its own expense. The Court did not endorse the High Court’s equation of that clause with frustration. The contractor’s appeal was dismissed and the connected appeal disposed of accordingly.

Issues

  1. Whether the award adopted a reasonably possible construction of the change-in-law clause.
  2. Whether the contract allocated ordinary diesel-price fluctuations to the contractor.
  3. Whether the change-in-law clause could be equated with frustration.

Provisions considered

Held

Result

Civil Appeal 673 of 2012 dismissed, leaving the High Court’s setting aside of the award intact. Civil Appeal 900 of 2012 disposed of in the same terms. No order as to costs.

Judgment PDF: Supreme Court of India, [2020] 4 S.C.R. 254.