Summary

The Supreme Court restored the preliminary notification and scheme for Dr. K. Shivaram Karanth Layout. The High Court had impermissibly imported Land Acquisition Act time limits into the Bangalore Development Authority Act contrary to the Constitution Bench ruling in Offshore Holdings. On the circumstances of proposed irregular exclusions and ensuing inquiries, the delay did not justify quashing the notification. Acquisition and an inquiry into official responsibility were directed.

Issues

  1. Whether delay in issuing the final declaration justified quashing the preliminary notification under the BDA Act.
  2. What directions were required concerning proposed land exclusions and responsibility for them.

Provisions considered

Held

Result

Appeals disposed of. High Court orders quashed; scheme and Section 17 notification upheld with acquisition, inquiry and reporting directions. Parties to bear their own costs.