Supreme Court of India · 19/08/2025

NABHA POWER LIMITED versus PUNJAB STATE POWER CORPORATION LIMITED AND OTHERS

[2025] 8 S.C.R. 1308 · 2025 INSC 1002

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Two power generators selected by tariff-based competitive bidding claimed that deemed export benefits under Para 8.3 of the Foreign Trade Policy 2009-14 were available to them on the bid cut-off date and that their subsequent withdrawal by the DGFT, and the Cabinet Press Release of 01.10.2009 on Mega Power Project thresholds, were 'Change in Law' events under Article 13 of their PPAs with PSPCL. Dismissing the appeals from APTEL, the Supreme Court held that the Press Release question was concluded by the three-Judge Bench decision in Nabha Power (only duly published notifications are 'law'), that an in-situ thermal power plant is neither 'goods' nor 'manufactured' and the appellants had shown no supply of goods under International Competitive Bidding, so no deemed export benefit was ever available, and that the DGFT notifications were merely clarificatory; no compensation was payable.

Issues

  1. Whether deemed export benefits under Para 8.3 of the Foreign Trade Policy 2009-2014 were legitimately available to the appellants on the bid cut-off date, and whether the DGFT notifications withdrawing them amounted to 'Change in Law' under the PPA.
  2. Whether the Press Release of the Cabinet decision of 01.10.2009 altering the Mega Power Project threshold constituted 'Change in Law' under the PPA.
  3. Whether the appellants were entitled to restitutionary compensation.

Provisions considered

Held

Result

Both civil appeals dismissed as devoid of merit; APTEL's common judgment dated 04.07.2017 rejecting the Change in Law claims of Nabha Power Ltd and Talwandi Sabo Power Ltd upheld; no order as to costs; pending applications disposed of.

Judgment PDF: Supreme Court of India, [2025] 8 S.C.R. 1308.