Supreme Court of India · 19/10/2023

THE CENTRAL WAREHOUSING CORPORATION versus THAKUR DWARA KALAN UL-MARUF BARAGLAN WALA

[2023] 14 S.C.R. 926 · 2023 INSC 940

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court replaced the High Court’s 15% cumulative annual escalation over eleven years with 8% cumulative escalation for valuing acquired land. With no usable contemporaneous exemplar, the earlier award supplied the base, but the long interval made a high uniform escalation unsafe. The Collector was directed to recalculate, recover any excess lawfully or pay any balance within two months of receipt of the judgment.

Issues

  1. What annual escalation fairly adjusted an earlier land valuation across an eleven-year interval.
  2. How payments already disbursed should be reconciled with the recalculated compensation.

Held

Result

Appeals allowed; High Court judgment set aside. Compensation to be recalculated using 8% cumulative annual escalation over the eleven-year gap, with lawful recovery of excess or payment of the balance within two months of receipt. No costs.

Judgment PDF: Supreme Court of India, [2023] 14 S.C.R. 926.