SNEHADEEP STRUCTURES PVT. LIMITED versus MAHARASHTRA SMALL SCALE INDUSTRIES DEVELOPMENT CORPORATION LTD.

[2024] 3 S.C.R. 454 · 2024 INSC 201

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Under the 1993 Act, Section 4’s non obstante clause overrides an agreement excluding interest but does not displace an agreed payment date. The later 120-day cap may apply to payments due after its commencement, but applicability and interest calculation here require findings on acceptance dates; the Court did not decide them.

Issues

  1. Does Section 4 override a contractual term fixing when payment is due, or only a term excluding interest?
  2. How does the 1998 amendment to Section 3 affect the contractual payment date and interest computation?
  3. What issues remain for any further interest or restitution proceedings after the arbitral award was set aside?

Provisions considered

Held

Result

Appeal dismissed; the setting aside of the arbitral award was affirmed. No order as to costs. MSSIDCL may seek restitution or execution, as advised, and enforce the security if SSPL does not refund the amount.