Summary

The Supreme Court retained the enhanced land-acquisition compensation but denied interest on that enhancement for the claimants’ delay of five and a half years in appealing. The unchallenged condonation order did not prevent that adjustment, even though it had imposed no interest condition. The acquiring public body could not be burdened with interest for delay not attributable to it. The remainder of the High Court’s judgment and award was confirmed.

Issues

  1. Whether unconditional condonation of the claimants’ delayed appeals required interest on enhanced compensation for the delay period.

Held

Result

Appeals partly allowed. High Court award modified only to deny interest on enhanced compensation for the period of delay in preferring the appeals; the rest of the judgment and award confirmed. No costs.