Summary

The Delhi High Court, relying on Pune Municipal Corporation, declared an acquisition lapsed under Section 24(2) of the 2013 Act because compensation had not been paid, while accepting that possession had been taken and the land put to use by the beneficiary department, and directed that the landowner be paid compensation under the 2013 Act. The Supreme Court set the judgment aside, holding that under the Constitution Bench in Indore Development Authority v. Manoharlal, which overruled Pune Municipal Corporation, there is no deemed lapse where possession was taken, and consequently the landowner is not entitled to compensation under the 2013 Act.

Issues

  1. Whether an acquisition lapses under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 where possession was admittedly taken and the land put to use but compensation was not paid, and whether the landowner can then claim compensation under the 2013 Act.

Provisions considered

Held

Result

Appeal allowed; High Court judgment dated 15.01.2018 in W.P.(C) No. 12143 of 2015 quashed and set aside; the writ petition dismissed; no order as to costs; pending applications disposed of.