Supreme Court of India · 12/04/2018

D. SARAVANAN versus SUPERINTENDING ENGINEER TANGEDCO TNEB DISTRIBUTION CIRCLE & ORS.

[2018] 3 S.C.R. 435 · 2018 INSC 330

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court directed consideration of an agricultural electricity application as registered from its corrected resubmission on 21 March 2011. The utility had returned the original application identifying only a missing Village Administrative Officer signature and could not benefit from failing to identify the unpaid registration fee as required by the statutory note. The applicant’s status as an advocate did not establish knowledge of every procedural requirement. He was to resubmit Rs. 550, and the utility was to communicate further requirements within three months.

Issues

  1. Whether the utility’s failure to identify the unpaid registration fee justified treating the application only as a fresh 2017 application.
  2. What registration date and consequential directions were appropriate.

Provisions considered

Held

Result

Appeal disposed of with registration effective 21 March 2011 for consideration; applicant to resubmit Rs. 550 demand draft, and utility to intimate further fees or requirements within three months.