Summary

In a miscellaneous application arising from the Court's 2018 order substituting an alternate apartment (No. 6503) for the one originally allotted to the respondent flat purchaser and alienated by the developer in breach of an NCDRC stay, the Court quantified what remained payable by the respondent after he had deposited the balance sale consideration and taken possession. Declining to decide each contested head, and weighing the developer's defaults against the fact that the balance consideration had remained with the purchaser, it fixed a lump sum of Rs.1,40,71,000 in lieu of all interest, taxes and other charges up to the date of possession.

Issues

  1. What amount was due and payable by the respondent purchaser to the appellant developer towards interest, taxes and other charges, after the balance sale consideration of Rs.3,72,35,401 had been deposited and possession of apartment No. 6503 handed over on 05.02.2025.

Provisions considered

Held

Result

Miscellaneous Application disposed of. Respondent to pay Rs.1,40,71,000 to the appellant within eight weeks of receipt of the order in full settlement of interest, taxes and other charges up to 05.02.2025; charges accruing after possession payable additionally; agreement/sale deed to be executed within two months of payment at the respondent's expense for stamp duty and registration; restriction on structural changes under order dated 10.12.2024 discharged.