Summary

In this 2019 decision, the Supreme Court held that the Section 11 appointment court had to impound an unstamped subcontract containing an arbitration clause before acting on it. The 2015 amendment restricting scrutiny to existence of an arbitration agreement did not displace mandatory stamp-law requirements. The arbitrator’s appointment was set aside and the matter remitted, with a procedure intended to reconcile stamp adjudication and expeditious disposal of the appointment application.

Issues

  1. Whether Section 11(6A) displaced the duty to impound an unstamped agreement before appointing an arbitrator.
  2. Whether separability allowed the arbitration clause to be acted upon despite the stamping defect.
  3. How stamp adjudication and speedy appointment were to be reconciled.

Provisions considered

Held

Result

Appeal allowed. Bombay High Court appointment judgment set aside and matter remitted for disposal in accordance with the impounding and stamp-payment procedure laid down in this judgment.