Supreme Court of India · 05/04/2018

M. P. POWER MANAGEMENT COMPANY LTD. versus RENEW CLEAN ENERGY PVT. LTD. & ANR.

[2018] 3 S.C.R. 829 · 2018 INSC 307

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court upheld the setting aside of termination of a solar power purchase agreement, while requiring the developer to pay Rs. 11,95,54,200 as contractual penalty within four weeks. The approved relocation, difficulties accessing the original site, substantial investment and advanced commissioning stage made termination arbitrary on these facts. The circumstances were expressly not treated as force majeure, and the developer remained liable for delay under clause 2.5.1. The disputed computation of the delay was left undecided.

Issues

  1. Whether termination was fair after approved relocation and substantial development of the solar project.
  2. Whether delay-related penalty remained payable despite setting aside termination.

Held

Result

Appeal dismissed without costs; termination remains set aside, but developer directed to pay Rs. 11,95,54,200 penalty within four weeks.

Judgment PDF: Supreme Court of India, [2018] 3 S.C.R. 829.