VIDARBHA IRRIGATION DEVELOPMENT CORPORATION versus M/S ANOJ KUMAR AGARWALA & ORS.

[2019] 2 S.C.R. 493 · 2019 INSC 83

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

A tender required a performance bank guarantee valid for forty months. The lowest bidder furnished one valid for six months and sought extension only after bids opened. This was a material deviation from an essential condition expressly reaffirmed at the pre-tender meeting; the bid could not subsequently be made responsive. Though critical of the High Court’s reasoning and conditional relief, the Court sustained rejection and directed the next bidder, on its undertaking, to execute the work at the lowest bid amount.

Issues

  1. Whether a six-month performance guarantee could be corrected after bid opening where forty months were mandatory.
  2. Whether a later government resolution or deference to the employer’s interpretation permitted condonation.
  3. What relief should follow rejection of the lowest bidder.

Held

Result

Civil appeals disposed of: rejection of respondent 2’s non-responsive bid sustained on the Supreme Court’s reasons; paragraph 8 of the High Court judgment set aside and work directed to respondent 1 at its undertaking to match Rs 39.15 crores.