Summary

In cross-contempt proceedings over a mediated settlement incorporated into its order, the Supreme Court held that all reciprocal obligations must be implemented together. The Mittal Group and TFIPL could not avoid the balance external-development-charge liability and frustrate licence renewal and separation of the projects. Their non-compliance was held deliberate and wilful, but further contempt orders were deferred to allow compliance. Counter-petitions against the Seth Group were dismissed.

Issues

  1. Whether the settlement and consent order required the Mittal Group and TFIPL to discharge the balance development-charge liability and related obligations.
  2. Whether the parties’ alleged defaults warranted contempt action and further compliance directions.

Held

Result

Two months from lifting of lockdown in the concerned area allowed for the directed compliance, failing which further contempt orders would follow against the Mittal Group and TFIPL. Contempt Petitions 257/2016 and 889/2017 dismissed; Contempt Petition 34/2016 directed to be listed before the same Bench after three months.