Summary

The Delhi High Court declared that the acquisition of a landowner's land had lapsed under Section 24(2) of the 2013 Act. It relied on Pune Municipal Corporation v. Harakchand Misirimal Solanki, solely because compensation had not been paid, although the DDA's case was that possession had already been taken. The Supreme Court set the judgment aside. The Constitution Bench in Indore Development Authority v. Manoharlal has overruled Pune Municipal Corporation. Under it, the "or" in Section 24(2) is read as "nor", so an acquisition lapses only where, through the authorities' inaction for five years or more before 1 January 2014, possession has not been taken and compensation has not been paid. Non-payment where possession has been taken causes no lapse. The writ petition was dismissed.

Issues

  1. Whether an acquisition lapses under Section 24(2) of the 2013 Act merely because compensation was not paid, where possession of the land had been taken.

Provisions considered

Held

Result

Appeal allowed; the Delhi High Court's judgment in W.P. (C) No. 10359 of 2015 declaring lapse set aside and the writ petition dismissed.