Supreme Court of India · 02/04/2024

LEVEL 9 BIZ PVT. LTD. versus HIMACHAL PRADESH HOUSING AND URBAN DEVELOPMENT AUTHORITY & ANOTHER

[2024] 4 S.C.R. 1 · 2024 INSC 257

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The High Court could not revive a cancelled public tender merely by accepting the authority’s and favoured bidder’s statements, disregarding an independent inquiry and earlier judicial findings of irregularities and technical ineligibility. The earlier successful challengers also required a hearing. The withdrawn letter of intent conferred no contractual right in this case. Finding mala fide collusion, the Supreme Court set aside the order, imposed Rs.5 lakh costs on HIMUDA and permitted a lawful fresh tender process.

Issues

  1. Whether consensual statements justified reviving the discredited tender.
  2. Whether the earlier challengers had to be joined and heard.
  3. Whether the withdrawn letter of intent created an enforceable right.
  4. What corrective relief and costs were warranted.

Provisions considered

Held

Result

Appeal allowed; High Court order set aside. HIMUDA to deposit Rs.5 lakh costs with the Supreme Court Advocates-on-Record Association within two weeks; lawful fresh tender process permitted.

Judgment PDF: Supreme Court of India, [2024] 4 S.C.R. 1.