Supreme Court of India · 24/08/2020

WG. CDR. ARIFUR RAHMAN KHAN AND ALEYA SULTANA AND ORS. versus DLF SOUTHERN HOMES PVT LTD. (NOW KNOWN AS BEGUR OMR HOMES PVT. LTD.) AND ORS.

[2020] 9 S.C.R. 136 · 2020 INSC 503

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Flat buyers were awarded additional compensation for prolonged delay in possession and failure to provide promised amenities. A one-sided agreement limiting delay compensation to Rs 5 per square foot per month did not foreclose the consumer forum’s power to award reasonable relief. Taking possession or executing conveyances did not extinguish the claims. Eleven specific settlements and three buyers who sold their interests were excluded. The Court awarded 6% simple annual interest for the stipulated delay period, in addition to contractual compensation, while rejecting challenges to tax interest, electricity and parking charges.

Issues

  1. Whether contractual delay compensation capped the consumer forum’s jurisdiction.
  2. Whether possession, conveyances, settlements or transfers barred the purchasers’ claims.
  3. Whether unprovided amenities and the disputed tax, electricity and parking demands constituted deficient service.

Provisions considered

Held

Result

Appeals partly allowed and NCDRC dismissal set aside. Additional compensation directed for eligible appellants, excluding eleven specific settlements and three transfers. Challenges to tax-interest, electricity and parking charges rejected; pending applications disposed of.

Judgment PDF: Supreme Court of India, [2020] 9 S.C.R. 136.