Supreme Court of India · 21/04/2025

LARSEN AND TOUBRO LIMITED versus PURI CONSTRUCTION PVT. LTD. AND OTHERS

[2025] 4 S.C.R. 2811 · 2025 INSC 523

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Cross-appeals by L&T and Puri Construction against the Delhi High Court Division Bench's Section 37 judgment were dismissed. The Supreme Court upheld the arbitral findings that the Supplementary Agreement was a non-starter for non-fulfilment of its conditions precedent and was tainted by economic coercion, that the Development Agreement was not novated and that L&T committed fundamental breach by abandoning the project; it also upheld the setting aside of the monetary awards (Rs. 35 crore, Rs. 75 crore, Rs. 5 crore and the Rs. 50 crore indemnity) as unsupported by evidence or contrary to Section 73 of the Contract Act. Bound by M. Hakeem, an award cannot be modified under Section 34 or 37; the costs direction was rightly severed and PCL left to pursue its remedy. The Court deprecated prolix arguments in Section 34/37 proceedings and called for time limits on oral submissions.

Issues

  1. Whether the Division Bench, in appeals under Section 37 of the Arbitration and Conciliation Act, 1996, could uphold part of the arbitral award while setting aside the monetary directions, and whether this amounted to an impermissible modification of the award.
  2. Whether the arbitral findings that the conditions precedent in the Supplementary Agreement were not fulfilled (so that it was a non-starter and did not novate the Development Agreement), that the Supplementary and Tripartite Agreements were tainted by economic coercion, and that L&T committed fundamental breach by abandoning the project, were open to interference under Sections 34 and 37.
  3. Whether the awards of Rs. 35 crore as damages, Rs. 75 crore in default of discharging the bank loan and securing release of title deeds, Rs. 5 crore for non-return of licences and permits, and the Rs. 50 crore indemnity for ITCREF's claims could be sustained.
  4. Whether the manner in which Section 34 petitions and Section 37 appeals are argued, with lengthy oral and written submissions and multiple citations, warrants restraint and time limits.

Provisions considered

Held

Result

All appeals (by L&T and by Puri Construction) dismissed; the Division Bench's judgment dated 30.04.2015 upheld, including the setting aside of the monetary directions in the award, the severed direction for costs of arbitration payable by L&T, the release of title deeds to PCL and the liberty to the parties to pursue their appropriate remedies under law.

Judgment PDF: Supreme Court of India, [2025] 4 S.C.R. 2811.