SUSHIL KUMAR AGARWAL versus MEENAKSHI SADHU & ORS.

[2018] 12 S.C.R. 756 · 2018 INSC 939

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court rejected a categorical bar on developers suing for specific performance, but dismissed this developer’s appeal. Under the pre-amendment provision, a developer with an interest in the property could sue subject to precise contractual work and inadequacy of monetary compensation. This agreement created no present interest in the land, left material construction terms vague and involved quantifiable expenditure adequately recompensable in money. The developer declined an alternative monetary claim, so no remand was warranted.

Issues

  1. Whether section 14(3)(c) categorically barred a developer’s suit against the landowner.
  2. Whether this development agreement met the conditions for specific performance.
  3. Whether an alternative monetary remedy required remand.

Provisions considered

Held

Result

Appeal dismissed; specific performance refused on the agreement’s facts, without a categorical bar on developers’ suits. No remand for monetary relief that the developer declined to seek. No order as to costs.

Judgment PDF: Supreme Court of India, [2018] 12 S.C.R. 756.