Supreme Court of India · 20/10/2022

JASPAL SINGH & OTHERS versus THE STATE OF HARYANA AND OTHERS

[2022] 15 S.C.R. 670 · 2022 INSC 1126

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

Land in village Jharli, Jhajjar, west of Bahu Road was acquired in 2007 for the Jhajjar Thermal Power Plant. The land just across the road had been acquired months earlier for Arawali Power Company, for which the Supreme Court had fixed Rs 25 lakh an acre. In one case, parts of the same survey number went to both projects. The Punjab and Haryana High Court cut the compensation back to the Collector's Rs 16 lakh, holding that the Arawali judgment's "not to be treated as precedent" remark barred reliance on it. The Supreme Court held that the lands were similarly situated, so such a disparity could not stand. The remark referred only to the parties' agreement to rely on sale deeds made after the Section 4 notification. Compensation was fixed at Rs 22 lakh an acre with statutory benefits, though some claimants who had filed late lost interest for the period of delay.

Issues

  1. Whether landowners whose land was acquired for the Jhajjar Thermal Power Plant were entitled to compensation comparable to that fixed for similarly situated land across the road acquired for Arawali Power Company, despite that judgment stating it was not to be treated as precedent.

Provisions considered

Held

Result

Appeals allowed; the High Court's common judgment modified and the landowners held entitled to Rs 22,00,000 per acre with all statutory benefits including interest, except that appellants in four specified first appeals get no interest for the delay in filing or refiling before the High Court; no order as to costs.

Judgment PDF: Supreme Court of India, [2022] 15 S.C.R. 670.