Supreme Court of India · 25/03/2019

WEST INTERNATIONAL CITY PVT LTD versus DEVASIS RUDRA

[2019] 2 S.C.R. 1070 · 2019 INSC 395

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court upheld a homebuyer’s refund after delay of nearly seven years beyond the extended possession deadline. Initially seeking possession did not oblige the buyer to wait indefinitely or defeat the alternative refund prayer. The one-sided contractual delay-interest clause did not preclude reasonable interest or compensation. The Court reduced refund interest from 12% to 9% per annum while affirming the National Commission’s remaining directions, including compensation.

Issues

  1. Whether the buyer could obtain refund despite initially seeking possession.
  2. Whether the contractual delay clause limited relief and what interest was appropriate.

Held

Result

Appeal disposed of with interest reduced to 9% per annum. Refund and the remaining National Commission directions, including Rs 2 lakh compensation, affirmed. Payment from the deposit directed; surplus to developer. No costs.

Judgment PDF: Supreme Court of India, [2019] 2 S.C.R. 1070.