Supreme Court of India · 03/01/2025

1. THE COMMISSIONER, BANGALORE DEVELOPMENT AUTHORITY 2. BANGALORE DEVELOPMENT AUTHORITY versus 1. SMT. RATHNAMMA 2. SRI G ARVIND 3. SMT. RADHAMMA

[2025] 1 S.C.R. 1683 · 2025 INSC 345

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

The Supreme Court held that landowners who voluntarily surrendered land to the Bangalore Development Authority in 2001, when the whole acquisition was completed before the amended incentive rules took effect on 27.11.2002, could not claim the larger entitlement under the amended rules merely because their application for sites was made in 2005. The allotment already made was confirmed and no further allotment was due.

Issues

  1. Whether entitlement to incentive sites for voluntary surrender of land is governed by the Incentive Rules in force when the surrender and acquisition were completed, or by the Amended Incentive Rules in force on the date of the application for allotment.
  2. Whether the respondents were entitled to an additional site beyond the sites already allotted to them.

Provisions considered

Held

Result

Appeal allowed; orders of the Single Judge and the Division Bench of the High Court set aside; the allotment of two 40 ft. x 60 ft. and two 40 ft. x 30 ft. sites already conveyed confirmed; respondents held not entitled to further allotment; no costs.

Judgment PDF: Supreme Court of India, [2025] 1 S.C.R. 1683.