Summary

In four appeals concerning land acquired for the planned development of Delhi, the Delhi High Court had declared the acquisitions lapsed under Section 24(2) of the 2013 Act, relying on Pune Municipal Corporation, because compensation had not been paid to the landowners, although in each case the State's stand that possession had been taken and handed over to the Delhi Development Authority was recorded. The Supreme Court set the orders aside, holding that under the Constitution Bench decision in Indore Development Authority v. Manoharlal, which overruled Pune Municipal Corporation, satisfaction of either condition, taking of possession or payment of compensation, saves the acquisition, and since possession had undisputedly been taken no other argument needed examination; the plea that the High Court orders should stand as they followed the law then prevailing was rejected.

Issues

  1. Whether acquisition proceedings lapse under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 where possession was taken but compensation was not paid.
  2. Whether High Court orders declaring lapse on the basis of Pune Municipal Corporation can be sustained after that decision was overruled.

Provisions considered

Held

Result

Appeals allowed; orders of the Delhi High Court declaring the acquisitions lapsed under Section 24(2) set aside; the writ petitions filed by the respondents dismissed.