UNION OF INDIA versus PARMAR CONSTRUCTION COMPANY

[2019] 5 S.C.R. 1009 · 2019 INSC 438

AI-generated headnote. Verify against the judgment before relying on it. Paragraph numbers refer to the judgment.

Summary

In these railway-contract arbitrations commenced before the 2015 amendment, the Supreme Court set aside appointments of independent arbitrators made without first respecting the agreed appointment procedure. The amended ineligibility provision did not govern merely because appointment applications were decided later. No-claim certificates did not extinguish the disputes on the prima facie circumstances of financial compulsion shown, and the remaining objections were left for arbitration.

Issues

  1. Whether the 2015 amendment governed the earlier arbitration requests.
  2. Whether the no-claim certificates established accord and satisfaction.
  3. Whether the High Court could bypass the agreed appointment mechanism on these facts.

Provisions considered

Held

Result

High Court appointment orders quashed. Railways directed to appoint under clause 64(3) within one month; contractors to submit claims within four weeks thereafter. Expedited arbitration directed without influence from the Court’s observations. Appeals disposed of without costs.

Judgment PDF: Supreme Court of India, [2019] 5 S.C.R. 1009.