Summary

The BOT road concession agreements were leases for stamp-duty purposes, and prior executive assurances did not defeat the subsequent legislative levy. However, the 2% duty applied only to expenditure attributable to the concessionaire under the agreement, excluding the State agency’s or another stakeholder’s contribution. The Court directed individual recalculation and appropriate refunds or payment of deficits.

Issues

  1. Whether BOT agreements granting toll-collection rights constituted leases liable to stamp duty.
  2. Whether the 2002 Madhya Pradesh rate amendment was invalid or barred by legitimate expectation or promissory estoppel based on earlier executive assurances.
  3. Whether duty could be assessed on the entire project cost rather than the concessionaire’s own expenditure.

Provisions considered

Held

Result

Appeals partly allowed without costs. Lease classification and statutory levy upheld; demands based on the entire project cost set aside to that extent. Individual recalculation directed within two months, with refunds within two months of determination or deficit payments within two months of fresh demand.