Summary

An appeal under Section 62 of the Insolvency and Bankruptcy Code, 2016 must be filed free of defects within the 45-day period plus the 15-day grace period. Defects in such an appeal must be cured within the 28 days allowed by the Supreme Court Rules, 2013, and the Court has no power to condone re-filing delay beyond that. The liquidator's appeal, filed 7 days late and re-filed after a further 82 days, was dismissed as time-barred.

Issues

  1. Whether the Supreme Court can condone delay in re-filing an appeal under Section 62 of the IBC when the defects are not cured within the 28 days permitted by the Supreme Court Rules, 2013.
  2. Whether the appellant's status as liquidator, or an earlier condonation of re-filing delay before the NCLAT in the same litigation, justifies a liberal approach or the exercise of power under Article 142.
  3. Whether sufficient cause was shown for the delay in filing and in re-filing the appeal.

Provisions considered

Held

Result

Appeal dismissed as time-barred, having been filed beyond the maximum period condonable under the IBC; applications for condonation of delay in filing and re-filing, and other connected applications, dismissed.