A decades-old claim for compensation for land taken by the State could not be disposed of without examining whether an award existed and how the offered amount was assessed. The High Court’s unexplained disbursement direction was not shown to be consensual. Property protection and the continuing deprivation required substantive examination despite delay. The appeal was allowed and the Letters Patent Appeal restored for fresh consideration, requested within two months.
Issues
- Whether delay justified refusing substantive examination of unpaid acquisition compensation.
- Whether an unexplained assessed amount and simple disbursement direction adequately resolved the claim.
Provisions considered
- Article 300-A, Constitution of IndiaProperty remains a constitutional and human right; lawful deprivation requires adherence to law and the obligation of compensation. These principles required substantive consideration of the long-unpaid acquisition claim. (¶¶ 17, 18, 19, 20, 21, 22, 23, 24)
- Articles 32 and 226, Constitution of IndiaDelay in constitutional remedies calls for judicial discretion informed by the breach, circumstances and relief; continuing wrong and compelling justice required examination rather than mechanical rejection. (¶¶ 25, 26, 27)
Held
- The High Court did not explain the basis or timing of the Rs.4,68,099 assessment, and nothing demonstrated the landowner’s consent to the order. It should have required the State to explain the failure to make a timely award and the prolonged delay in determining compensation, preserving the owner’s opportunity to challenge quantum. (¶¶ 12, 13, 14, 15, 16)
- Although property ceased to be a fundamental right, it remains protected under Article 300-A and as a human right. The State must follow lawful acquisition procedures and pay reasonable compensation; welfare-State status does not permit taking property beyond constitutional and statutory authority. (¶¶ 17, 18, 19, 20, 22, 23, 24)
- Delay and laches require a judicious, reasonable assessment of the particular circumstances, including a continuing cause of action and a wrong shocking the judicial conscience. Constitutional jurisdiction has no prescribed limitation period; compelling demands for justice warrant its exercise to advance justice. Mechanical rejection without asking whether fair compensation was paid was erroneous here. (¶¶ 25, 26, 27)
- The impugned order was set aside and Letters Patent Appeal 997/2019 restored for fresh hearing of both sides in light of these observations. The Court requested disposal within two months; it did not itself fix the final compensation payable. (¶¶ 28, 29, 30)
Result
Appeal allowed; High Court order set aside and Letters Patent Appeal restored for fresh consideration. Disposal requested within two months.