Summary

By consent, the Supreme Court appointed a sole arbitrator to decide all claims and counterclaims under a wind-farm development agreement, replacing its three-member tribunal arrangement. Arbitration was to proceed under the 1996 Act through the Madras High Court Arbitration Centre, subject to the arbitrator’s required independence and availability declarations. The contractor’s pending Facilitation Council proceeding was directed to close. The disposition rested on the parties’ agreement rather than a merits ruling on the High Court’s view of MSMED counterclaims.

Issues

  1. How the agreed reference to a court-appointed sole arbitrator should be implemented.

Held

Result

Appeal disposed of by consent with appointment of a sole arbitrator and closure of the identified Facilitation Council proceeding.