Summary

HSVP had to deposit 80% of the audited debt due for the Gurgaon rapid-metro projects in escrow under the High Court’s consent arrangement. Pending fraud investigations and objections to the financial audit did not justify withholding that deposit. Disputes over the audit, termination and inter-party claims remained arbitrable. The Supreme Court ordered deposit within three months, prohibited appropriation without permission, and preserved ongoing investigations.

Issues

  1. Whether pending investigations and audit objections permitted the public authorities to withhold the agreed escrow deposit.
  2. Whether writ intervention was justified despite contractual arbitration provisions and which disputes remained for arbitration.

Provisions considered

Held

Result

Appeals disposed of with directions for escrow deposit within three months and consequential documentation. High Court writ petitions disposed of; arbitral remedies and ongoing investigations preserved. No costs.